Corbierre Ave. Ph. 1, Tekoppel to Ingle

This project involves the replacement of 8" water main with 1,042 LF of 8" from Tekoppel Avenue to Ingle Avenue. This relocation is in preparation for road improvements planned for this area as part of the Lloyd4U project.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

​

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

​

Project Designer - Lochmueller Group

Evansville, Indiana

​

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

​

Contractor- Ragle, Inc.

Newburgh, Indiana

​

​

Road Closures and Boil Advisories

Click HERE

Project Update
  •     Recent Progress (March 9 to March 16)
    •    Ragle performed hydrostatic testing and chlorinated the new 8” water main between Tekoppel Ave and Walker Ave on Corbierre Ave.   

​

  •     Anticipated Activities for the Upcoming Week (March 16 to March 22)  
    •    Ragle intends to active the new main on Corbierre between Tekoppel and Walker.
    •    Ragle intends to start service relocations on Corbierre between Tekoppel and Walker.
    •    Ragle intends to start installation of the new 8” C-900 water main on Corbierre between Walker and Ingle.   

Active and Scheduled Closures

Active​

  • Corbierre between Tekoppel and Ingle

​

Scheduled

  • ​No additional closures scheduled in the immediate future. 

​

Project Schedule​

  • Install and test water main from Tekoppel to Walker - February 5 to March 14, 2025

  • Install and test water main from Walker to Ingle - March 17 to March 28, 2025

  • Install services on new water main - March 31 to April 11, 2025

  • Abandon existing water main - April 14 to April 18, 2025