South Evergreen Acres




 This project involves the replacement of 4" and 6” water main with 5,280 LF of 8” water main in South Evergreen Acres Neighborhood.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
​
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
​
Project Designer - Three i Design
Evansville, Indiana
​
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
​
Contractor- Infrastructure Systems, Inc.
Orleans, Indiana
​
​
Project Update
​​​​​​
-
Recent Progress (March 16 to March 22)
• Infrastructure Systems completed lawn restoration activity throughout the project site.
• Infrastructure Systems excavated trenches and prepared for HMA installation.
​
-
 Anticipated Activities for Upcoming Week (March 23 to March 29)
• E&B Paving intends to complete the installation of HMA base and HMA surface throughout the project site.
• MAMCO intends to complete the milling of the existing pavement throughout the project site.
Active and Scheduled Closures
• Active
-
Pine Creek Drive from Old State Rd. to Heather Place- Local Traffic Only
-
Heather Place from Pine Creek Drive to Pine Place- Local Traffic Only ​
-
Heather Court from Pine Place to Dead End- Local Traffic Only
-
Pine Place from Heather Place to Larch Lane - Local Traffic Only
-
Larch Lane, W. Evergreen Road to Holly Hill Drive – Local Traffic Only
​
• Scheduled
-
No additional closures scheduled at this time.
​
Project Schedule​
-
Pine Creek Dr. from 8201 Pine Creek Dr. to Old State Road
-
Water Main installation COMPLETE
-
Water Service Connections COMPLETE
-
Final Connections COMPLETE
-
Restoration from 3/3/25 - 3/14/25
-
-
​Pine Creek Dr. from Heather Place to 8201 Pine Creek Dr.
-
Water Main installation COMPLETE
-
Water Service Connections COMPLETE
-
Final Connections COMPLETE
-
Restoration from 3/3/25 - 3/14/25
-
-
Heather Place from Pine Place to Pine Creek Drive
-
​Water Main installation COMPLETE
-
Water Service Connections COMPLETE
-
Final Connections COMPLETE
-
Restoration from 3/10/25 - 3/14/25
-
-
Heather Court from Pine Place to cul-de-sac
-
​Water Main installation COMPLETE
-
Water Service Connections COMPLETE
-
Final Connections COMPLETE
-
Restoration from 3/10/25 - 3/14/25
-
-
Pine Place from Larch Lane to Heather Place
-
​Water Main installation COMPLETE
-
Water Service Connections COMPLETE
-
Final Connections COMPLETE
-
Restoration from 3/17/25 - 3/21/25
-
-
Pine Place from Larch Lane to cul-de-sac
-
​Water Main installation COMPLETE
-
Water Service Connections COMPLETE
-
Final Connections COMPLETE
-
Restoration from 3/17/25 - 3/21/25
-
-
Larch Lane from Pine Place to 8235 Larch Lane
-
Water Main installation COMPLETE
-
Water Service Connections COMPLETE
-
Final Connections COMPLETE
-
Restoration from 3/24/25 - 3/28/25
-
-
Larch Lane from Evergreen Road to Pine Place
-
​Water Main installation COMPLETE
-
Water Service Connections COMPLETE
-
Final Connections COMPLETE
-
Restoration from 3/24/25 - 3/28/25
-