South Evergreen Acres

   This project involves the replacement of 4" and 6” water main with 5,280 LF of 8” water main in South Evergreen Acres Neighborhood. 

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

​

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

​

Project Designer - Three i Design

Evansville, Indiana

​

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

​

Contractor- Infrastructure Systems, Inc.

Orleans, Indiana

​

​

Project Update

​​​​​​

  •  Recent Progress (March 16 to March 22)
    •    Infrastructure Systems completed lawn restoration activity throughout the project site.
    •    Infrastructure Systems excavated trenches and prepared for HMA installation.

​

  •     Anticipated Activities for Upcoming Week (March 23 to March 29)  
    •    E&B Paving intends to complete the installation of HMA base and HMA surface throughout the project site.
    •    MAMCO intends to complete the milling of the existing pavement throughout the project site.

     

Active and Scheduled Closures

•    Active

  • Pine Creek Drive from Old State Rd. to Heather PlaceLocal Traffic Only 

  • Heather Place from Pine Creek Drive to Pine PlaceLocal Traffic Only  â€‹

  • Heather Court from Pine Place to Dead EndLocal Traffic Only 

  • Pine Place from Heather Place to Larch Lane - Local Traffic Only 

  • Larch Lane, W. Evergreen Road to Holly Hill Drive – Local Traffic Only

​

•    Scheduled

  • No additional closures scheduled at this time. 

​

Project Schedule​

  • Pine Creek Dr. from 8201 Pine Creek Dr. to Old State Road 

    • Water Main installation COMPLETE

    • Water Service Connections COMPLETE

    • Final Connections COMPLETE

    • Restoration from 3/3/25 - 3/14/25

  • ​Pine Creek Dr. from Heather Place to 8201 Pine Creek Dr.

    • Water Main installation COMPLETE

    • Water Service Connections COMPLETE

    • Final Connections COMPLETE

    • Restoration from 3/3/25 - 3/14/25

  • Heather Place from Pine Place to Pine Creek Drive 

    • ​Water Main installation COMPLETE

    • Water Service Connections COMPLETE

    • Final Connections COMPLETE

    • Restoration from 3/10/25 - 3/14/25

  • Heather Court from Pine Place to cul-de-sac 

    • ​Water Main installation COMPLETE

    • Water Service Connections COMPLETE

    • Final Connections COMPLETE

    • Restoration from 3/10/25 - 3/14/25

  • Pine Place from Larch Lane to Heather Place

    • ​Water Main installation COMPLETE

    • Water Service Connections COMPLETE

    • Final Connections COMPLETE

    • Restoration from 3/17/25 - 3/21/25

  • Pine Place from Larch Lane to cul-de-sac

    • ​Water Main installation COMPLETE

    • Water Service Connections  COMPLETE

    • Final Connections COMPLETE

    • Restoration from 3/17/25 - 3/21/25

  • Larch Lane from Pine Place to 8235 Larch Lane  

    • Water Main installation COMPLETE

    • Water Service Connections COMPLETE

    • Final Connections COMPLETE

    • Restoration from 3/24/25 - 3/28/25

  • Larch Lane from Evergreen Road to Pine Place 

    • ​Water Main installation  COMPLETE

    • Water Service Connections COMPLETE

    • Final Connections COMPLETE

    • Restoration from 3/24/25 - 3/28/25